SLC report on damages for personal injury
The Scottish Law Commission has published a report proposing reforms to modernise and simplify personal injury damages law in Scotland.
READ MOREClause 8.9.3 of the JCT Design and Build Contract (2016 Edition) provides that the Contractor is entitled to terminate its employment under the building contract in circumstances where:
Clause 8.9.4 provides the Contractor with a further right to terminate the building contract where there has been a repeated specified default. In its unamended form, this clause reads as follows:
“If the Contractor for any reason does not give the further notice referred to in clause 8.9.3, but (whether previously repeated or not):
then, upon or within a reasonable time after such repetition, the Contractor may by notice to the Employer terminate the Contractor’s employment under this Contract.”
The key question was whether the Contractor could rely upon repeated failures by the Employer to make timely payments and terminate the building contract under clause 8.9.4, even if previous non-payments were remedied before the right to terminate under clause 8.9.3 arose.
The facts of this case can be summarised as follows:
Having scrutinised the terms of clause 8.9.4, the Court of Appeal overturned the High Court’s first decision and held that the termination notice was valid. Lord Justice Stuart-Smith, giving the concurrent opinion of the court, stated that:
“the natural meaning of the conditional words at the commencement of Clause 8.9.4 are clear: “If the Contractor … does not give the further notice referred to in Clause 8.9.3” are broad enough to cover any state of affairs other than one where the Contractor does give notice”.
Lord Justice Stuart-Smith also relied upon the decision of the TCC in Reinwood Ltd v L Brown & Sons Ltd [2007] BLR 10, based on the 1998 edition of the standard form,where Judge Gilliland held that:
“… a notice of determination may be given as soon as the specified default has been repeated. There is nothing unreasonable in that, since the employer has already received a warning in respect of the previous default and must be taken to know that if he repeats the default he runs the risk that the contract may be determined either forthwith or within a reasonable time after the repetition of the specified default.”
Lord Justice Stuart-Smith noted that this decision “renders the Employer’s ice thinner from the outset”, making it easier for Contractors to terminate their employment when faced with repeated late payments.
Whilst clauses 8.9.3 and 8.9.4 of the standard form building contract used in Providence Building Services Ltd were subject to bespoke amendments (the time periods referred to at those clauses being revised by the parties), nothing in the Court of Appeal’s decision appears to have turned on those amendments. As such, we can expect this decision to be of assistance to Contractors on projects using JCT or SBCC standard form building contracts with similar or identical termination provisions.
Stay informed